Week 8 Update

The play structure is fully installed and the safety surfacing is nearly complete. Once all of the spongy surface is poured, artificial turf will be installed to cover the entire southwest corner of the play yard. Landscaping areas now have mulch added and more plants are being installed with each passing day. The first of our new trees were also planted this week. The irrigation system is connected to the building water supply and it will soon be delivering water to all landscaping and new grass areas. Sod for the grass lawns will start being installed next week. As all of the areas on the south side of the building near completion, focus will also shift to the new sport court over the next couple of weeks.